The Town of Orangeville has started their Water Meter Upgrade Project, with installations being carried out in different areas over the next several months.
Important Information:
- Appointment Booking: Wait for your appointment letter before booking. If you’ve received your letter, schedule your appointment within a week.
- Travel Plans: Check the project map and tentative schedule at orangeville.ca/WaterMeters to see if your vacation might affect your appointment. If there’s a conflict, notify Orangeville Hydro at 519-942-8000.
Tentative Schedule:
- Proof of Concept Area: July 2024
- Zone 1: July to mid-October 2024
- Zone 2: mid-October to December 2024
- Zone 3: December 2024 to mid-January 2025
- Zone 4: mid-January to March 2025
- Zone 5: March to end of April 2025
Please note that timelines may shift. For the latest updates, CLICK HERE.